Lutheran Brethren Fellowship Church

Ceramic tile work on walls have begun. Casework and cabinetry is 85% complete. The outside clean up is ready for placing exterior concrete sidewalks and

Crane Creek Tennis Facility

Site utilities have been installed, and the building foundation and slab have been placed. The erection of the pre-engineered metal building is completing. Site retaining

Caldwell Commons

Site utilities, CMU walls and structural steel are complete. Site concrete, roofing and canopies have begun. Paving and landscaping will begin late April.